North McGregor Avenue Work Starts Monday, With Full Reopening Promised by Christmas

Crews begin work Monday on North McGregor Avenue between Springhill Avenue and the Museum Drive roundabout, adding resurfacing, drainage, sidewalks and lighting, with the full roadway reopening between Thanksgiving and Christmas.

Illustration for the news story: North McGregor Avenue Work Starts Monday, With Full Reopening Promised by Christmas

Work begins Monday, Sept. 14, on North McGregor Avenue in Mobile, and drivers who use it should plan on lane closures through the fall.

According to a City of Mobile news release, crews will improve the road from Springhill Avenue to the roundabout on Museum Drive.

What the Project Includes

  • Resurfacing
  • Drainage improvements
  • New sidewalks
  • New lighting

That combination is more than a repaving job. Drainage and lighting are the elements that determine whether a resurfaced road stays in good condition and whether it is usable after dark, and sidewalks change who can use the corridor at all.

Traffic Impacts

Officials said they will close one lane of traffic at a time, with detours available.

Keeping a lane open in each direction is the least disruptive approach available on a corridor like this one, though it also extends the schedule relative to a full closure.

The Holiday Window

The city built a specific accommodation into the schedule.

“The project will begin early next week with crews opening up the full roadway to traffic between Thanksgiving and Christmas,” the release said.

That is a deliberate pause. The stretch between Springhill Avenue and Museum Drive runs near heavily used destinations, and the weeks between Thanksgiving and Christmas carry the year’s highest traffic volumes. Reopening the full roadway for that window and resuming afterward trades a slightly longer overall schedule for a considerably less painful holiday season.

Completion

Work is expected to be completed by spring 2027.

Drivers should plan alternate routes where practical during lane closures, and pedestrians should expect sidewalk access along the corridor to change as construction moves.

Update: How the First Week Is Phased

The Mobile City Council has provided additional detail on how the opening week of work will proceed.

On Monday, the contractor will mobilize and install traffic control signs. That is setup rather than construction — staging equipment and putting the signage in place that will govern the work zone for the duration of the project.

Later in the week, weather permitting, work will begin at the north end of the corridor near Spring Hill Avenue. That phase will include some temporary road closures.

The distinction matters for drivers planning the week. Monday’s activity should produce little more than new signs appearing along the route. The closures arrive with the start of actual work at the north end.

Officials are asking drivers to plan ahead and allow extra time when traveling through the area, and said they will continue to provide updates as work progresses and traffic impacts change.

Update: McGregor Avenue Project Enters Its Final Phase

The McGregor Avenue Project has moved into its final phase, Mobile City Councilman Beau Fleming told residents in his District 5 newsletter this week.

Crews have begun removing the old asphalt near Spring Hill Avenue. This last phase runs from Spring Hill Avenue north to the roundabout.

“I know construction can be an inconvenience, especially for those who use North McGregor regularly,” Fleming wrote. “Please slow down, pay attention to changing traffic patterns, and give crews plenty of room to work safely.”

“We still have work ahead, but seeing this final phase get underway is a good sign of the progress being made,” he added, thanking District 5 residents for their patience.

Drivers should continue to expect shifting lane patterns and temporary closures along North McGregor Avenue while the final phase is underway.