Steel for Gulf Shores Pedestrian Bridge Arrives in Waterway Village; December Lift Planned Over Intracoastal Waterway

The superstructure for the 75-foot Gulf Shores pedestrian bridge was delivered Nov. 17 to East 2nd Street. Crews will partly assemble it on the ground before a planned December installation.

Illustration of steel bridge sections staged at a construction site beside the Intracoastal Waterway in Gulf Shores
Illustration

GULF SHORES, Ala. — The steel that will form the main span of the Gulf Shores pedestrian bridge over the Intracoastal Waterway is now on site. Crews took delivery of the bridge superstructure on Tuesday, Nov. 17, staging it on the north side of East 2nd Street at the construction site beside the canal.

Over the next few weeks, workers will put part of the structure together on the ground. The city plans to lift it into place in December, and the overall project is expected to be finished next year.

Ground Assembly First, Then the Lift

Rather than arriving as a single finished piece, the superstructure will be partially assembled at ground level before it is hoisted onto its supports. Building large sections on the ground is a common approach for bridges over working waterways, because it lets crews do much of the fitting and bolting in a controlled setting and limits the time equipment must work over the channel.

Residents and visitors passing the site should not expect the steel they see now to resemble the finished bridge. The city has cautioned that substantial work remains. Temporary steel bracing will stay attached to the structure until the arch is complete, and that bracing will be removed only after the permanent elements are in place.

Project timeline at a glance

  • Nov. 17, 2026: Superstructure delivered to the north side of East 2nd Street.
  • Late November into December: Partial assembly on the ground at the construction site.
  • December 2026: Planned installation of the superstructure over the waterway.
  • 2027: Expected completion of the bridge project.

A 75-Foot Crossing Linking Waterway Village

When finished, the bridge will rise about 75 feet above the Intracoastal Waterway near Alabama 180 and East 2nd Street. Its purpose is to tie together the north and south halves of Waterway Village, the Gulf Shores district that straddles the canal and is home to waterfront restaurants and gathering spots such as Tacky Jack’s, Acme Oyster House, Big Beach Brewing and LuLu’s.

The span is meant to give walkers and cyclists a dedicated route of their own between the two sides of the district, separate from vehicle traffic.

The height is dictated by the waterway below. The Gulf Intracoastal Waterway is a federally maintained navigation channel used by commercial barge traffic as well as recreational boats, so any fixed crossing must leave enough clearance for vessels to pass underneath.

Stairs, elevators and lighting

Getting people up and over a 75-foot structure requires more than a ramp. Each end of the bridge will have a stairway and a large elevator sized to carry several pedestrians and bicyclists at the same time, so riders will not have to carry bikes up the stairs and people with limited mobility can cross easily.

Decorative lighting is part of the design as well. The city intends for the illuminated span to serve as a recognizable landmark at night.

Plazas and Street Work Around the Bridge

The bridge is the centerpiece of a broader set of improvements in Waterway Village. New public plazas are planned at both landings, where the stair and elevator towers meet the ground. Plans call for those spaces to include:

  • Public restrooms
  • Shaded seating areas
  • Gathering and event space
  • Views of the waterfront

Street improvements are also planned along East 2nd Street and Gulf Pines, including wider sidewalks, on-street parking, upgraded lighting and other features meant to make the area more comfortable for people on foot.

The city has described the combined work as an effort to build a safer and more connected Waterway Village and Gulf Shores community, and has thanked residents for their patience during construction.

Cost and Earlier Schedule Changes

South AL News has previously reported on the project’s budget and timing. Earlier this fall, city officials told the City Council that the bridge’s opening would shift from January to March so that the plazas at its base could be finished first. Officials said at the time that the bridge structure itself would be done before March, but the city intends to hold off on opening it until the plaza work is complete.

That plaza work added roughly $1.28 million to the contract with Harrison Construction through a change order, raising the overall bridge project cost from $24.7 million to nearly $26 million. In January, the city accepted a $3.6 million grant through the Gulf of Mexico Energy Security Act, known as GoMESA, for the plazas, though estimates put that portion of the work at about $4.8 million.

GoMESA shares a portion of federal revenue from offshore oil and gas leasing with Gulf Coast states, which in turn direct money to coastal projects. Alabama has used the program to pay for a wide range of coastal conservation, recreation and infrastructure work.

Part of a Larger Push to Remake the District

Waterway Village sits along the Intracoastal Waterway in the heart of Gulf Shores, north of the beach. For several years the city has been working to turn the area into a walkable town center with restaurants, shops and public spaces connected to the water.

Alongside the bridge, the city has been rebuilding blocks of East 2nd Street as a complete street, a design approach that gives room to people walking, cycling and riding golf carts rather than focusing mainly on cars. Earlier in November, the council considered a contract of up to $3 million to rebuild the block between East 22nd and East 23rd avenues with new pavement, parking, a landscaped median, wide sidewalks and new drainage and water lines. The city has said it wants the corridor finished before the bridge opens. The city has also introduced rebate incentives intended to draw new investment such as restaurants and boutique hotels to Waterway Village and the Beach Walking District.

What to Expect Near the Site

With assembly under way, the area around East 2nd Street on the north side of the canal will remain an active construction zone through the coming weeks. Drivers, cyclists and pedestrians should expect heavy equipment and crews at work, should follow posted signs and should stay out of fenced areas.

The December lift will mark one of the most visible milestones of the project. After the superstructure is set, crews will still need to complete the arch, remove the temporary bracing and finish the towers, lighting and plazas before the crossing opens to the public next year.

For more on related work in the district, see our coverage of the East 2nd Street rebuild.